In a standard crane hire agreement, the Hirer will plan the lift, select a suitable crane, specify the slinging and signaling arrangements, supervise the lift and be responsible for the lifting operation.

The Hirer should also have adequate insurance to cover any loss or damage to the crane or equipment whilst the crane is under the control of the hirer.

If you require any support with the planning or selection of the crane, we would be happy to send one of our engineers to aid with this. However, this should not be interpreted as taking responsibility for planning the overall lifting operation. If you would like to see more comprehensive details regarding the C.P.A terms of standard hire of crane, please use the link below.

All lifting operations are to be properly planned before they are carried out, in accordance with regulation 8 of L.O.L.E.R